Project Status Reports

Title Report Date Time Cost Scope Overall Change
Report for April 2023 April 2023 BLUE BLUE BLUE BLUE No Change
Report for March 2023 March 2023 GREEN GREEN GREEN GREEN Within Tolerance
Report for February 2023 February 2023 GREEN GREEN GREEN GREEN Within Tolerance
Report for January 2023 January 2023 GREEN GREEN GREEN GREEN Moderate
Report for December 2022 December 2022 GREEN GREEN GREEN GREEN
Report for November 2022 November 2022 GREEN GREEN GREEN GREEN No Change
Report for October 2022 October 2022 GREEN GREEN GREEN GREEN No Change
Report for September 2024 September 2022 GREEN GREEN GREEN GREEN

Project Info

Project
Worktribe Upgrades v2022.7 and v2023.1
Code
RIS024
Programme
Research Information Systems (RIS)
Management Office
ISG PMO
Project Manager
Chris Konczak
Project Sponsor
Dominic Tate
Current Stage
Close
Status
Closed
Project Classification
Run
Start Date
22-Sep-2022
Planning Date
20-Oct-2022
Delivery Date
23-Mar-2023
Close Date
27-Apr-2023
Programme Priority
2
Overall Priority
Normal
Category
Compliance

Documentation