Report for February 2023

Report Date
February 2023

Achievements in last period

  • No achievements - project was waiting on the next release of Worktribe - v2023.1 which is due at the end of January / beginning of  February
  • A date move was decided early February to start the upgrades after the industrial action period had ended.
  • Worktribe booked to carry out the DEV on 8th March @ 10:30, TEST and LIVE upgrades on 3rd April @ 14:30 and 17:30

Issues

  • None

Next Steps

  • Worktribe to carry out the DEV upgrade on 08/03/2023
  • Testing / UAT to be carried out during the remainder of March

Milestones

v2023.1 DEV Upgrade 08-Mar-2023
Testing (UAT) on DEV complete 31-Mar-2023
Delivery v2023.1 TEST and LIVE upgrade    03-Apr-2023
Deployment Sign off Review 14-Apr-2023
Project Closure 20-Apr-2023
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Time
Within Tolerance
Cost
No Change
Scope
No Change
Overall
Within Tolerance
Has formal escalation taken place?
No
Change Commentary
Deployment moved out from 23/03/2023 to 03/04/2023
Activity
Approved budget
25.0 days
Activity this month
3.5 days
Activity this year
17.0 days
Activity to date
17.0 days
Estimate to complete current year
8.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Worktribe Upgrades v2022.7 and v2023.1
Code
RIS024
Programme
Research Information Systems (RIS)
Management Office
ISG PMO
Project Manager
Chris Konczak
Project Sponsor
Dominic Tate
Current Stage
Close
Status
Closed
Project Classification
Run
Start Date
22-Sep-2022
Planning Date
20-Oct-2022
Delivery Date
23-Mar-2023
Close Date
27-Apr-2023
Programme Priority
2
Overall Priority
Normal
Category
Compliance

Documentation