Report for March 2023
- Report Date
- March 2023
Achievements in last period
- Worktribe successfully completed the DEV upgrade to v2023.1.
- UAT testing is currently underway, no major issues have been reported
- Service alert is live for 06/04/2023 and Go-Cab agreed as a minor change.
Issues
- LIVE upgrade was booked with Worktribe, but had to be rescheduled delayed from 03/04/2023 to 06/04/2023. This is due to ERO availability.
Next Steps
- Worktribe to carry out the TEST and LIVE upgrades on 06/04/2023 at 14:30 and 17:30
- Checks to be completed on 07/04/2023
- Start project closure process
Milestones
Delivery v2023.1 TEST and LIVE upgrade | 06-Apr-2023 |
Deployment Sign off Review | 14-Apr-2023 |
Project Closure | 20-Apr-2023 |
- Approved budget
- 25.0 days
- Activity this month
- 3.0 days
- Activity this year
- 20.0 days
- Activity to date
- 20.0 days
- Estimate to complete current year
- 4.5 days
- Estimate to complete future years
- 0.0 days