Report for March 2023

Report Date
March 2023

Achievements in last period

  • Worktribe successfully completed the DEV upgrade to v2023.1. 
  • UAT testing is currently underway, no major issues have been reported
  • Service alert is live for 06/04/2023 and Go-Cab agreed as a minor change. 

Issues

  • LIVE upgrade was booked with Worktribe, but had to be rescheduled delayed from 03/04/2023 to 06/04/2023. This is due to ERO availability. 

Next Steps

  • Worktribe to carry out the TEST and LIVE upgrades on 06/04/2023 at 14:30 and 17:30
  • Checks to be completed on 07/04/2023
  • Start project closure process

Milestones

 

Delivery v2023.1 TEST and LIVE upgrade   06-Apr-2023
Deployment Sign off Review 14-Apr-2023
Project Closure 20-Apr-2023
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Time
Within Tolerance
Cost
No Change
Scope
No Change
Overall
Within Tolerance
Has formal escalation taken place?
No
Change Commentary
Delivery date rescheduled from 03/04/2023 to 06/04/2023
Activity
Approved budget
25.0 days
Activity this month
3.0 days
Activity this year
20.0 days
Activity to date
20.0 days
Estimate to complete current year
4.5 days
Estimate to complete future years
0.0 days

Project Info

Project
Worktribe Upgrades v2022.7 and v2023.1
Code
RIS024
Programme
Research Information Systems (RIS)
Management Office
ISG PMO
Project Manager
Chris Konczak
Project Sponsor
Dominic Tate
Current Stage
Close
Status
Closed
Project Classification
Run
Start Date
22-Sep-2022
Planning Date
20-Oct-2022
Delivery Date
23-Mar-2023
Close Date
27-Apr-2023
Programme Priority
2
Overall Priority
Normal
Category
Compliance

Documentation