Research Information Management changes frequently, with changes to Research Excellence Framework, Open Access requirements and increasing demand from Research Funders and our own researchers.

Pure and the service that it offers needs to be kept up to date. This can be achieved by taking the major version releases of Pure each year. Additionally, Pure will only support redundant features for one year following their deprecation. It is vital that the University’s installation of Pure is kept up to date to avoid major step changes.

This project is a follow-on project from the RIS027.

The scope of this Pure project is to upgrade the University’s installation for the following versions 5.30 and 5.31 ensuring that it continues to operate as expected including:

  • Testing of the Pure processes adopted by the University
  • Testing of the Interfaces presenting data to Pure from People & Money (Finance, and HR), VRS and Student Systems
  • Testing of the outgoing interfaces to the Pure widget and EdWeb
  • This will include the first upgrade following Pure migration to the Cloud

Current project status

Report Date RAG Budget Effort Completed Effort to complete
January 2025 GREEN 50.0 days 2.6 days 47.4

Project Info

Project
Pure Annual Upgrades 24/25
Code
RIS039
Programme
Research Information Systems (RIS)
Management Office
ISG PMO
Project Manager
David Watters
Project Sponsor
Dominic Tate
Current Stage
Plan
Status
In Progress
Start Date
27-Jan-2025
Planning Date
20-Feb-2025
Delivery Date
30-Jun-2025
Close Date
31-Jul-2025
Overall Priority
Normal

Documentation

Not available.

Project Dashboard

Project journal

No entries found.

Change dashboard

Nothing to report.