November 2016
- Report Date
- November 2016
Achievements in Last Period
- move to full Cloud service - not delivered
- start on second and final tranche of GPGPU - started
Issues and Risks
none - but we do have a general Programme Level issue around the impact of the cluster problems on the project team resourcing for all RSS projects
Next Steps
- move to full Cloud service
- start on second and final tranche of GPGPU
We have a delay due to folk having to be diverted to resolving the cluster issues (AFM). Also, we feel that it would be a better launch to wait until the cluster service had returned to normal.
Project status RED as the delivery date for New Service has been moved back to end of January to allow for resolution of major cluster service issues.
Future Milestones
31-Oct-2016 | Eddie Enhancements : Two 3TB Large Memory Systems - Available as Service |
25-Jan-2016 | Cloud Service : Full Production Service |
7-Dec-2016 | Eddie Enhancements : GPGPU Acceptance Sign-Off |
27-Jan-2017 | GPGPU Available for Service |
10-Feb-2017 | Closure |
- Approved budget
- 0.0 days
- Activity this month
- 0.0 days
- Activity this year
- 0.0 days
- Activity to date
- 0.0 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 0.0 days