Equipment ordered
- Report Date
- May 2016
Achievements in Last Period
- Disk infrastructure - Order Placed.
- Backup infrastructure - Order Placed.
Issues and Risks
- Delivery dates may slip based around availability.
Next Steps
- Begin physical installation of delivered equipment
Future Milestones
03-Jun-2016 | Equipment delivered |
29-Jul-2016 | Capacity added to IGMM file system |
31-Jul-2016 | Project close |
- Approved budget
- 0.0 days
- Activity this month
- 0.0 days
- Activity this year
- 0.0 days
- Activity to date
- 0.0 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 0.0 days