Disk Delivered, Backup Infrastructure Delivered and Installed.

Report Date
June 2016

Achievements in Last Period

  • Disk infrastructure - Delivered
  • Backup infrastructure - Delivered and installed.

Issues and Risks

  • Disk infrastructure yet to be physically installed and tested.

Next Steps

  • Begin physical installation of disk infrastructure.
  • Test and add to filesystem.

 

Future Milestones

29-Jul-2016Capacity added to IGMM file system
31-Jul-2016Project close
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
IGMM DataStore capacity expansion
Code
RSS014
Programme
ITI - Research Services (RSS)
Project Manager
Kevin Tomlinson
Project Sponsor
David Perry
Current Stage
Close
Status
Closed
Start Date
14-Dec-2015
Planning Date
n/a
Delivery Date
n/a
Close Date
29-Jul-2016
Programme Priority
11

Documentation