Objectives.

Replace existing Datastore Storage that is coming to end of supported life. The first half was replaced last year (Phase 1). This has been purchased, is in the rack, data migrated and all redundant kit removed and disposed of.

We are currently on Phase 2.

Purchase Kit - Complete.

Deliver Kit - Complete

Rack and Stack - Complete.

Integrate into Datastore - Complete.

Migrate Data from historic kit onto new - In Progress.

Remove redundant kit from racks and dispose of - To be planned.

 

 

Current project status

Report Date RAG Budget Effort Completed Effort to complete
June 2018 GREEN 0.0 days 0.0 days 0.0

Project Info

Project
DataStore Expansions
Code
RSS027
Programme
ITI - Research Services (RSS)
Management Office
ISG PMO
Project Manager
Andy Todd
Project Sponsor
David Fergusson
Current Stage
Close
Status
Closed
Start Date
01-May-2017
Planning Date
n/a
Delivery Date
n/a
Close Date
01-Aug-2018
Programme Priority
13
Overall Priority
Normal
Category
Discretionary

Documentation

Project Dashboard

Project journal

No entries found.

Change dashboard