Project Brief

Document Sign-off

Name Role Date signed off
David Fergusson Project Sponsor  
Andrew Todd Project Manager  
Maurice Franceschi Programme Manager  

 

 

Background and Scope.

Replace existing Datastore Storage that is coming to end of supported life. The first half was replaced last year (Phase 1). This has been purchased, is in the rack, data migrated and all redundant kit removed and disposed of.

We are currently on Phase 2.

Purchase Kit - Complete.

Deliver Kit - Complete

Rack and Stack - Complete.

Integrate into Datastore - Complete.

Migrate Data from historic kit onto new - In Progress.

Remove redundant kit from racks and dispose of - To be planned.

 

Out of Scope

Removal of redundant kit will be arranged through the Enterprise team.

 

Objectives and Deliverables and Success Criteria

  Description of the Objective Success Criteria
     
Define an Order Agree specification of kit and agree order with vendor.  Specification Agreed with Research Systems Team and Appropriate kit ordered. 
      
Deliver Have Kit delivered and installed to allow enough of a window to complkete migration of data before end of year. Complete by mid April.
      
Migrate onto new kit and dispose of redundant kit. Migration in progress. Available for use by the end of July.

  

   

 

 

Benefits

No datastore kit will be outwith support contract.

 

Project Team

Role Name Division / Group / Team / College / School and Title
Project Manager Andrew Todd  
Technical Lead Kevin Tomlinson  
Additional Technical. Jan Winter

 

Project Info

Project
DataStore Expansions
Code
RSS027
Programme
ITI - Research Services (RSS)
Management Office
ISG PMO
Project Manager
Andy Todd
Project Sponsor
David Fergusson
Current Stage
Close
Status
Closed
Start Date
01-May-2017
Planning Date
n/a
Delivery Date
n/a
Close Date
01-Aug-2018
Programme Priority
13
Overall Priority
Normal
Category
Discretionary

Documentation

Deliver