Project Brief
Document Sign-off
Name | Role | Date signed off |
---|---|---|
David Fergusson | Project Sponsor | |
Andrew Todd | Project Manager | |
Maurice Franceschi | Programme Manager |
Background and Scope.
Replace existing Datastore Storage that is coming to end of supported life. The first half was replaced last year (Phase 1). This has been purchased, is in the rack, data migrated and all redundant kit removed and disposed of.
We are currently on Phase 2.
Purchase Kit - Complete.
Deliver Kit - Complete
Rack and Stack - Complete.
Integrate into Datastore - Complete.
Migrate Data from historic kit onto new - In Progress.
Remove redundant kit from racks and dispose of - To be planned.
Out of Scope
Removal of redundant kit will be arranged through the Enterprise team.
Objectives and Deliverables and Success Criteria
Description of the Objective |
Success Criteria | |
Define an Order | Agree specification of kit and agree order with vendor. | Specification Agreed with Research Systems Team and Appropriate kit ordered. |
Deliver | Have Kit delivered and installed to allow enough of a window to complkete migration of data before end of year. | Complete by mid April. |
Migrate onto new kit and dispose of redundant kit. | Migration in progress. | Available for use by the end of July. |
|
Benefits
No datastore kit will be outwith support contract.
Project Team
Role | Name | Division / Group / Team / College / School and Title |
---|---|---|
Project Manager | Andrew Todd | |
Technical Lead | Kevin Tomlinson | |
Additional Technical. | Jan Winter |