Report For April 2018
- Report Date
- April 2018
Achievements in Last Period
- Ordered PDUs for Appleton Tower install. As yet delivery date unclear.
- Removed Phase 1 Storage from Network by end of week ending 27th April.
- Old racks moved out of the way at Appleton Tower (P.Hutton).
- Storage Physically Removed from Racks (JCMB).
- Arranged removal and destruction of redundant kit.
- The storage owned by has been held back and they need to arrange to pick up.
Issues
Key Tasks For next period
- Rack and Stack New Kit (Phase 2) by Weekend ending 11th May (Dell) JCMB.
- Call / Meeting with IBM to Agree process to migrate Metadata.
- Agree Plan to Migrate Metadata.
- Further planning required to fully commission and move data onto the storage by end of June.
- Plan removal of Phase 2 Redundant kit from Racks and destruction.
Milestones
Target Date | Previous Date | Title | Stage | |
---|---|---|---|---|
04-May-2018 | No date available | Agree Plan to Migrate Metadata | Execute | |
31-May-2018 | No date available | Rack and Stack New Kit (Phase 2) JCMB will be done by 11th May. | Deliver | |
29-Jun-2018 | No date available | Phase 2 redundant kit fully drained | Deliver | |
27-Jul-2018 | No date available | Remove drained (Phase 2) kit from racks and dispose. | Deliver | |
31-Jul-2018 | No date available | Closure | Close |
- Approved budget
- 0.0 days
- Activity this month
- 0.0 days
- Activity this year
- 0.0 days
- Activity to date
- 0.0 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 0.0 days