Report For April 2018

Report Date
April 2018

Achievements in Last Period

  • Ordered PDUs for Appleton Tower install. As yet delivery date unclear.
  • Removed Phase 1 Storage from Network by end of week ending 27th April.
  • Old racks moved out of the way at Appleton Tower (P.Hutton).
  • Storage Physically Removed from Racks (JCMB).
  • Arranged removal and destruction of redundant kit.
  • The storage owned by has been held back and they need to arrange to pick up.

 

Issues

 

Key Tasks For next period

  • Rack and Stack New Kit (Phase 2) by Weekend ending 11th May (Dell) JCMB.
  • Call / Meeting with IBM to Agree process to migrate Metadata.
  • Agree Plan to Migrate Metadata.
  • Further planning required to fully commission and move data onto the storage by end of June.
  • Plan removal of Phase 2 Redundant kit from Racks and destruction.

 

 

Milestones

Target Datesort descending Previous Date Title Stage  
04-May-2018 No date available Agree Plan to Migrate Metadata Execute

view

31-May-2018 No date available Rack and Stack New Kit (Phase 2) JCMB will be done by 11th May. Deliver

view

29-Jun-2018 No date available Phase 2 redundant kit fully drained Deliver

view

27-Jul-2018 No date available Remove drained (Phase 2) kit from racks and dispose. Deliver

view

31-Jul-2018 No date available Closure Close

view

 

 

 

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
DataStore Expansions
Code
RSS027
Programme
ITI - Research Services (RSS)
Management Office
ISG PMO
Project Manager
Andy Todd
Project Sponsor
David Fergusson
Current Stage
Close
Status
Closed
Start Date
01-May-2017
Planning Date
n/a
Delivery Date
n/a
Close Date
01-Aug-2018
Programme Priority
13
Overall Priority
Normal
Category
Discretionary

Documentation