Report For June 2018
- Report Date
- June 2018
Achievements in Last Period
- Metadata migration complete. IBM on site for 5 days working with Jan.
- Phase 2 kit in JCMB racked, stacked and configured.
- Phase 2 data migration under way and should complete on Target.
Issues
Key Tasks For next period
- Complete migration of Phase 2 data.
- Plan to remove and dispose of redundant kit from Phase 2 migration.
- Project Closure
Milestones
Target Date | Previous Date | Title | Stage | Complete | |
---|---|---|---|---|---|
29-Jun-2018 | No date available | Phase 2 redundant kit fully drained | Deliver | No | |
27-Jul-2018 | No date available | Remove drained (Phase 2) kit from racks and dispose. | Deliver | No | |
31-Jul-2018 | No date available | Closure | Close | No |
- Approved budget
- 0.0 days
- Activity this month
- 0.0 days
- Activity this year
- 0.0 days
- Activity to date
- 0.0 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 0.0 days