As part of the Data Safe Haven project. It was agreed that backup infrastructure would be required in a alternative site to primary Data Safe Haven server site, the ACF at the Easter Bush Campus. It was agreed that the new Backup Infrastructure would be located at JCMB data Centre at the Kings Buildings Campus. Additionally, as part of this deliverable we would expand the capability of the existing TS3500 at the ACF by adding two additional expansion tape racks. This is complete.

 

Update (2018 Budget).

An additional Tape Rack extension and 4 tape drives were purchased and installed. This was complete April 2018.

 

Update (June 2018).  - 2 New Extentions.

  • Further budget was identified and it was decided to add an additional two extension racks onto the TS4500 at JCMB before the equipment is caged, which will happen next financial year.

 

TSM Upgrade.

  • There is also an outstanding piece of work required to Upgrade the Tivoli (TSM)  Libraries. This will be carried out in August and September, depending on the change freeze.

The current task list for this is as follows;

Phase 1

- Shutdown existing tsm

- repatch existing tsm into new storage fabric*

- repatch tape library into new storage fabric*

- Confirm and / or repatch admin09 networking as necessary

- TBC - zone tapes from library into all hosts - Configure tape drives on all hosts

- Configure library manager

- point all hosts including existing tsm to library manager

- make sure network connectivity

- bring up existing tsm in the infrastructure and cross fingers

Phase 2

- New plan to start splitting data up in existing instance across the multiple new machines in the new architecture.

This is very high level and the plan will be refined and reviewed over the next few weeks.

 

 

Current project status

Report Date RAG Budget Effort Completed Effort to complete
July 2019 BLUE 0.0 days 0.0 days 0.0

Project Info

Project
Backup Infrastructure Upgrade
Code
RSS029
Programme
ITI - Research Services (RSS)
Management Office
ISG PMO
Project Manager
Andy Todd
Project Sponsor
David Fergusson
Current Stage
Close
Status
Closed
Project Classification
Grow
Start Date
20-Apr-2017
Planning Date
01-Jun-2018
Delivery Date
28-Jun-2019
Close Date
26-Jul-2019
Overall Priority
Higher
Category
Compliance

Documentation

Project Dashboard

Project journal

No entries found.

Change dashboard

Nothing to report.