Report For December 2017

Report Date
December 2017

Achievements in Last Period

  • All infrastructure installed.
  • All networking tasks complete.

 

Issues and Risks

 

Key Tasks For Next Period  

The delivery strategy is to get Data Safe Haven backing up to disk by the end of December. The December task list below with achieve this. By the end of January, in line with the first Data Safe Haven pilots going live, the target is to have Data Safe Haven and other, current backup objects being backed up to the new backup stale and tape drive.

 

  • Disable backups  on the current platform.
  • Allow disk pools to drain to tape (multiple days)
  • Leaving us with an idle and drained system.
  • Database backup to tape
  • All data and metadata now in the tape library
  • Configure tape library into the new backup fabric.
  • Configure all new hosts to see tape library.
  • Configure new hosts to use the new library manager as the library broker.
  • Import / DR the database backup we made into a new instance on the new platform.
  • Open for business (firewall rules, client reconfigs pending).

 

Future Milestones

Target Datesort descending Previous Date Title Stage Complete  
31-Jan-2018 No date available Have DSH backing up to Tape. Deliver No

view

28-Feb-2018 No date available Migrate all residual backup objects to new Infrastructure. Deliver No

view

16-Mar-2018 No date available Closure Close No

view

 

Project Status
RAG Status
Time
AMBER
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Backup Infrastructure Upgrade
Code
RSS029
Programme
ITI - Research Services (RSS)
Management Office
ISG PMO
Project Manager
Andy Todd
Project Sponsor
David Fergusson
Current Stage
Close
Status
Closed
Project Classification
Grow
Start Date
20-Apr-2017
Planning Date
01-Jun-2018
Delivery Date
28-Jun-2019
Close Date
26-Jul-2019
Overall Priority
Higher
Category
Compliance

Documentation