Report For February 2018

Report Date
February 2018

Achievements in Last Period

  • All infrastructure installed.
  • All networking tasks complete.
  • Data Safe Haven backing Up Successfully.

 

Issues and Risks

 

Key Tasks For Next Period  

The next key task will be to upgrade the Tivoli library for existing (non DSH) projects.

This should have been done by now but has been delayed by strike action.

Ian Wilkes to complete design and support documentation.

 

Future Milestones  

Target Datesort descending Previous Date Title Stage Complete  
30-Mar-2018 No date available Migrate all existing backup projects to new Library. Deliver No

view

30-Mar-2018 No date available Complete outstanding Documentation. Deliver No

view

13-Apr-2018 No date available Closure Close No

view

 

Project Status
RAG Status
Time
AMBER
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Backup Infrastructure Upgrade
Code
RSS029
Programme
ITI - Research Services (RSS)
Management Office
ISG PMO
Project Manager
Andy Todd
Project Sponsor
David Fergusson
Current Stage
Close
Status
Closed
Project Classification
Grow
Start Date
20-Apr-2017
Planning Date
01-Jun-2018
Delivery Date
28-Jun-2019
Close Date
26-Jul-2019
Overall Priority
Higher
Category
Compliance

Documentation