Report For April 2018

Report Date
April 2018

Achievements in Last Period

  • All infrastructure installed.
  • All networking tasks complete.
  • Data Safe Haven backing Up Successfully.

 

Issues and Risks

Refsort descending Date Identified Type Short Description Governance Required  
1 02-May-2018 Issue Network Changes dependant on Data Safe Haven work. No

view

 

Key Tasks For Next Period  

  • Until the above Data Safe Haven Work is carried out (i.e. Post August) , these tasks cannot progress.
    • The next key task will be to upgrade the Tivoli library for existing (non DSH) projects.
    • This should have been done by now but has been delayed by strike action.
    • Ian Wilkes to complete design and support documentation.

 

Future Milestones  

Target Datesort descending Previous Date Title Stage Complete  
29-Jun-2018 No date available Publish Re plan taking Data Safe haven delay into account. Plan No

view

28-Sep-2018 No date available Migrate all existing backup projects to new Library. Deliver No

view

26-Oct-2018 No date available Complete outstanding Documentation. Deliver No

view

30-Nov-2018 No date available Closure Close No

view

 

Project Status
RAG Status
Time
RED
Cost
GREEN
Scope
AMBER
Overall
RED
RAG Commentary
Issue - Migration to new Tape Library dependent on Data Safe Haven changes which are not happening until August. Project replanning accordingly.
Change Status
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Backup Infrastructure Upgrade
Code
RSS029
Programme
ITI - Research Services (RSS)
Management Office
ISG PMO
Project Manager
Andy Todd
Project Sponsor
David Fergusson
Current Stage
Close
Status
Closed
Project Classification
Grow
Start Date
20-Apr-2017
Planning Date
01-Jun-2018
Delivery Date
28-Jun-2019
Close Date
26-Jul-2019
Overall Priority
Higher
Category
Compliance

Documentation