Report For May2018
- Report Date
- May 2018
Achievements / Changes in Last Period
Only change in the last month has been additional budget granted to the tape backup infrastructure to add two addition extension tracks.
In addition to the above, to support the data Centre hot / cold row initiative, the tape rack will need to be moved to another row.
Both of the above are currently being planned and it hs been agreed that the associated capital budget may carry over into next financial year.
Issues and Risks
Ref![]() |
Date Identified | Type | Short Description | Governance Required | |
---|---|---|---|---|---|
1 | 02-May-2018 | Issue | Network Changes dependant on Data Safe Haven work. | No |
Key Tasks For Next Period
- Until the above Data Safe Haven Work is carried out (i.e. Post August) , these tasks cannot progress.
- The next key task will be to upgrade the Tivoli library for existing (non DSH) projects.
- This should have been done by now but has been delayed by strike action.
- Ian Wilkes to complete design and support documentation.
Plan to move the tape rack to the assigned row.
Plan to add the two extension racks onto the tape rack.
Future Milestones
Target Date![]() |
Previous Date | Title | Stage | Complete | |
---|---|---|---|---|---|
29-Jun-2018 | No date available | Publish Re plan taking Data Safe haven delay into account. | Plan | No | |
28-Sep-2018 | No date available | Migrate all existing backup projects to new Library. | Deliver | No | |
26-Oct-2018 | No date available | Complete outstanding Documentation. | Deliver | No | |
30-Nov-2018 | No date available | Closure | Close | No |
- Approved budget
- 0.0 days
- Activity this month
- 0.0 days
- Activity this year
- 0.0 days
- Activity to date
- 0.0 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 0.0 days