Report For June 2018

Report Date
June 2018

Achievements / Changes in Last Period

Additional Tape Racks.

    Two additional tapes racks ordered and delivery is planned for the 19th of July.

    Resource planned to come on site the following day. Move the existing infrastructure and add the two new extensions.

 

TSM Library Upgrade

    Initial planning call with the TSM Engineer (Ian Wilkes).

    Initial networking tasks required planned for W/B 13th August.

    Ian Wilkes on site for two weeks from the 20th of August.

    Plan will be further refined over the next couple of weeks.

 

Issues and Risks

Refsort descending Date Identified Type Short Description Governance Required  
1 02-May-2018 Issue Network Changes dependant on Data Safe Haven work. No

view

 

Key Tasks For Next Period  

Additional Tape Racks.

    Move the tape rack to the assigned row.

    Add the two extension racks onto the tape rack.

TSM Library Upgrade

    Initial networking tasks required planned for W/B 13th August.

    Ian Wilkes on site for two weeks from the 20th of August.

    Plan will be further refined over the next couple of weeks.

 

Future Milestones  

Target Datesort descending Previous Date Title Stage Complete  
29-Jun-2018 No date available Publish Re plan taking Data Safe haven delay into account. Plan No

view

28-Sep-2018 No date available Migrate all existing backup projects to new Library. Deliver No

view

26-Oct-2018 No date available Complete outstanding Documentation. Deliver No

view

30-Nov-2018 No date available Closure Close No

view

 

Project Status
RAG Status
Time
AMBER
Cost
GREEN
Scope
AMBER
Overall
AMBER
Change Status
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Backup Infrastructure Upgrade
Code
RSS029
Programme
ITI - Research Services (RSS)
Management Office
ISG PMO
Project Manager
Andy Todd
Project Sponsor
David Fergusson
Current Stage
Close
Status
Closed
Project Classification
Grow
Start Date
20-Apr-2017
Planning Date
01-Jun-2018
Delivery Date
28-Jun-2019
Close Date
26-Jul-2019
Overall Priority
Higher
Category
Compliance

Documentation