Report For July 2018
- Report Date
- July 2018
Achievements / Changes in Last Period
Additional Tape Racks.
Tape rack relocated in the JCMB Computer Room.
Two additional racks added and infrastructure re surveyed for the Secure Cage deployment.
TSM Library Upgrade
Initial planning call held with the TSM Engineer (Ian Wilkes).
Ian will be onsite for two weeks from the 20th of August.
Pre work required by Stephen Giles should be complete by the 17th.
Key Tasks For Next Period
TSM Library Upgrade
Initial networking tasks required planned for W/B 13th August.
Ian Wilkes on site for two weeks from the 20th of August.
Plan will be further refined over the next couple of weeks.
Future Milestones
Target Date | Previous Date | Title | Stage | Complete | |
---|---|---|---|---|---|
29-Jun-2018 | No date available | Publish Re plan taking Data Safe haven delay into account. | Plan | No | |
28-Sep-2018 | No date available | Migrate all existing backup projects to new Library. | Deliver | No | |
26-Oct-2018 | No date available | Complete outstanding Documentation. | Deliver | No | |
30-Nov-2018 | No date available | Closure | Close | No |
- Approved budget
- 0.0 days
- Activity this month
- 0.0 days
- Activity this year
- 0.0 days
- Activity to date
- 0.0 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 0.0 days