Report For August 2018

Report Date
August 2018

Achievements / Changes in Last Period

 

 

TSM Library Upgrade

Ian Wilkes has been on-site this week.

patched adm09 (The old Tivoli Server) to the Data Safe Haven Infrastructure.

Get TSM Ops Centre working for admin09.

Fix and test cross site backups (ACF <-> JCMB)

Get local tape copy of all Data Safe haven Data.

Lock Down TSM as per issue raised by Penetration Test.

 

Key Tasks For Next Period  

TSM Library Upgrade

Install GPFS on ACF Infrastructure.

Ian to create TSM Containers on the new platform as per the agreed design

Agree and Test Container Migration Process.  ‘Turn the handle’ type migrations. i.e. everything tested and in place beforehand (while Ian is here).

Plan to retire redundant kit.

Documentation.

 

Future Milestones  

Stage Milestone Due Date Previous Date Complete  
Deliver Migrate all existing backup projects to new Library. 28-Sep-2018 No date available No

view

Deliver Complete outstanding Documentation. 26-Oct-2018 No date available No

view

Close Closure 30-Nov-2018 No date available No

view

 

Project Status
RAG Status
Time
AMBER
Cost
AMBER
Scope
GREEN
Overall
AMBER
RAG Commentary
Current delays on this project are generally down to lack of resource in the Systems Team. We didn't get GPFS installed on time to enable the Tivoli Consultant to fully test a migration process. We may look at the possibility of getting the Tivoli Consultant to backfill the tasks that we need the Systems team to carry out.
Change Status
Has formal escalation taken place?
No
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Backup Infrastructure Upgrade
Code
RSS029
Programme
ITI - Research Services (RSS)
Management Office
ISG PMO
Project Manager
Andy Todd
Project Sponsor
David Fergusson
Current Stage
Close
Status
Closed
Project Classification
Grow
Start Date
20-Apr-2017
Planning Date
01-Jun-2018
Delivery Date
28-Jun-2019
Close Date
26-Jul-2019
Overall Priority
Higher
Category
Compliance