Report For November 2018
- Report Date
- November 2018
Achievements / Changes in Last Period
This has been impacted by the requirement from ACF to move the Infrastructure containing the existing backup storage 'admin09' from the row it’s in at the ACF.
This has necessitated that we copy the admin09 library from the old kit to the Data Safe Haven based infrastructure before the end of Nov 19.
This migration was problematic but ultimately successful.
This will however necessitate a re plan of the other outstanding work required on the platform.
Key Tasks For Next Period
Re plan migrating the TSM Data from the Admin09 database into the new containers as per the original plan.
Future Milestones
Stage | Milestone | Due Date | Previous Date | Complete | |
---|---|---|---|---|---|
Deliver | Migrate all existing backup projects to new Library. | 31-Dec-2018 | No date available | No | |
Deliver | Complete outstanding Documentation. | 31-Jan-2019 | No date available | No | |
Close | Closure | 28-Feb-2019 | No date available | No |
- Approved budget
- 0.0 days
- Activity this month
- 0.0 days
- Activity this year
- 0.0 days
- Activity to date
- 0.0 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 0.0 days