Report For November 2018

Report Date
November 2018

Achievements / Changes in Last Period

This has been impacted by the requirement from ACF to move the Infrastructure containing the existing backup storage 'admin09' from the row it’s in at the ACF.

This has necessitated that we copy the admin09 library from the old kit to the Data Safe Haven based infrastructure before the end of Nov 19.

This migration was problematic but ultimately successful.

This will however necessitate a re plan of the other outstanding work required on the platform.

 

Key Tasks For Next Period  

 

Re plan migrating the TSM Data from the Admin09 database into the new containers as per the original plan.

 

Future Milestones  

Stage Milestone Due Date Previous Date Complete  
Deliver Migrate all existing backup projects to new Library. 31-Dec-2018 No date available No

view

Deliver Complete outstanding Documentation. 31-Jan-2019 No date available No

view

Close Closure 28-Feb-2019 No date available No

view

 

Project Status
RAG Status
Time
AMBER
Cost
AMBER
Scope
GREEN
Overall
AMBER
RAG Commentary
Current delays on this project are generally down to lack of resource in the Systems Team. We didn't get GPFS installed on time to enable the Tivoli Consultant to fully test a migration process. We may look at the possibility of getting the Tivoli Consultant to backfill the tasks that we need the Systems team to carry out.
Change Status
Time
Moderate
Cost
No Change
Scope
No Change
Overall
Moderate
Has formal escalation taken place?
No
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Backup Infrastructure Upgrade
Code
RSS029
Programme
ITI - Research Services (RSS)
Management Office
ISG PMO
Project Manager
Andy Todd
Project Sponsor
David Fergusson
Current Stage
Close
Status
Closed
Project Classification
Grow
Start Date
20-Apr-2017
Planning Date
01-Jun-2018
Delivery Date
28-Jun-2019
Close Date
26-Jul-2019
Overall Priority
Higher
Category
Compliance

Documentation