Report For December 2018

Report Date
December 2018

Achievements / Changes in Last Period

Work related to moving the Cabinet at the ACF is now Complete.

We have a preplanning session on the 17th with Ian Wilkes on site for 2 week from 11th Of February.

 

Key Tasks For Next Period  

Re plan migrating the TSM Data from the Admin09 database into the new containers as per the original plan.

We have some additional tasks to add to the plan that were left over from the Piece Of Work to move the Cabinet.

Once the re planning session has happened I'll communicate the now completion date.

 

 

Future Milestones  

Stage Milestone Due Date Previous Date Complete  
Deliver Migrate all existing backup projects to new Library. 31-Dec-2018 No date available No

view

Deliver Complete outstanding Documentation. 31-Jan-2019 No date available No

view

Close Closure 28-Feb-2019 No date available No

view

 

Project Status
RAG Status
Time
AMBER
Cost
AMBER
Scope
GREEN
Overall
AMBER
RAG Commentary
Now the Rack Move work is complete. We have a re planning session for the Library break up next week. Once that happened, I'll communicate the new completion date.
Change Status
Time
Moderate
Cost
No Change
Scope
No Change
Overall
Moderate
Has formal escalation taken place?
No
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Backup Infrastructure Upgrade
Code
RSS029
Programme
ITI - Research Services (RSS)
Management Office
ISG PMO
Project Manager
Andy Todd
Project Sponsor
David Fergusson
Current Stage
Close
Status
Closed
Project Classification
Grow
Start Date
20-Apr-2017
Planning Date
01-Jun-2018
Delivery Date
28-Jun-2019
Close Date
26-Jul-2019
Overall Priority
Higher
Category
Compliance

Documentation