Report For March 2019

Report Date
March 2019

Achievements / Changes in Last Period

Work related to moving the Cabinet at the ACF is now Complete.

We have a preplanning session on the 17th with Ian Wilkes on site for 2 week from 11th Of February.

 

Key Tasks For Next Period  

Install and configure additional tape drives on TS3500 @ ACF

Complete process definition and test of migrating from the old TSM Library to the new broken down libraries.

Enable the TS4500 @ JCMB for Datavault.

 

 

 

Future Milestones  

Stage Milestone Due Date Previous Date Complete  
Deliver Complete outstanding Documentation. 27-Feb-2019 No date available No

view

Deliver Migrate all existing backup projects to new Library. 28-Jun-2019 No date available No

view

Close Closure 26-Jul-2019 No date available No

view

 

Project Status
RAG Status
Time
AMBER
Cost
AMBER
Scope
AMBER
Overall
AMBER
RAG Commentary
We now have a clear path ahead with the migration of the TSM Libraries. This should probably be reviewed with a view to closing down this project and opening another with a more accurate scope.
Change Status
Time
Moderate
Cost
No Change
Scope
Moderate
Overall
Moderate
Has formal escalation taken place?
No
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Backup Infrastructure Upgrade
Code
RSS029
Programme
ITI - Research Services (RSS)
Management Office
ISG PMO
Project Manager
Andy Todd
Project Sponsor
David Fergusson
Current Stage
Close
Status
Closed
Project Classification
Grow
Start Date
20-Apr-2017
Planning Date
01-Jun-2018
Delivery Date
28-Jun-2019
Close Date
26-Jul-2019
Overall Priority
Higher
Category
Compliance