Report For June 2017

Report Date
June 2017

Achievements in Last Period

  • Design Complete and Infrastructure Order Agreed.
  • Clarified IBM Spectrum Licence requirements for Data Safe Haven.
  • Agreed that the IBM Tape Rack can go into the JCMB Data Centre.

 

Issues and Risks

Refsort descending Raised On Type Short Description Governance Required Date Completed  
1 04-Jul-2017 Issue Issue Raising PO in accounts Team No  

view

2 04-Jul-2017 Issue Lack of Clarity on Where the Tape Rack Will be Located in the JCMB Data Centre. No  

view

 

Key Tasks For Next Period;

  • Once orders are placed, confirm delivery dates from vendors and confirm availability dates of engineers.
  • Progress pre work required in the data centers including removing redundant kit in the ACF DC.
  • Plan Data Centre implementations in conjunction with other projects and suppliers.
  • Complete planning phase, including implementation planning and begin delivery.
  • Continue to manage budgets and communications.

 

Future Milestones

Target Datesort descending Previous Date Title Stage Complete  
07-Jul-2017 No date available End Of Planning. Plan No

view

14-Jul-2017 No date available Infrastructure Delivery. Execute No

view

28-Jul-2017 No date available Closure Close No

view

 

Project Status
RAG Status
Time
AMBER
Cost
GREEN
Scope
GREEN
Overall
AMBER
Change Status
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Backup Infrastructure Upgrade
Code
RSS029
Programme
ITI - Research Services (RSS)
Management Office
ISG PMO
Project Manager
Andy Todd
Project Sponsor
David Fergusson
Current Stage
Close
Status
Closed
Project Classification
Grow
Start Date
20-Apr-2017
Planning Date
01-Jun-2018
Delivery Date
28-Jun-2019
Close Date
26-Jul-2019
Overall Priority
Higher
Category
Compliance

Documentation