Report For August 2017

Report Date
August 2017

Achievements in Last Period

  • Ventis Rack Delivered and installed at JCMB.
  • Dell Support Stacks Racked and Stacked by Dell Engineers and both Sites.
  • Planning cried out with Dell for remote Install.

 

Issues and Risks

  • Physical install not 100% complete. Cabling still outstanding.

 

Key Tasks For Next Period;

  • Complete Cabling within the data centres.
  • Complete Dell Remote Install.
  • Initiate Tivoli Install and Configuration.

 

 

Future Milestones

Target Datesort descending Previous Date Title Stage Complete  
08-Sep-2017 No date available Complete Cabling within the data centres. Deliver No

view

29-Sep-2017 No date available Complete Dell Remote Install. Build No

view

14-Oct-2017 No date available Complete Tivoli Install and Configuration. Integrate No

view

18-Oct-2017 No date available Complete all Build & Test Activities. Deliver No

view

20-Oct-2017 18-Aug-2017 Closure Close No

view

 

Project Status
RAG Status
Time
AMBER
Cost
GREEN
Scope
GREEN
Overall
AMBER
RAG Commentary
Delays in the Dell Physical Install caused by Cabling not being in place has had knock on impact with the remote install. Ideally we'll look to make some of this time up.
Change Status
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Backup Infrastructure Upgrade
Code
RSS029
Programme
ITI - Research Services (RSS)
Management Office
ISG PMO
Project Manager
Andy Todd
Project Sponsor
David Fergusson
Current Stage
Close
Status
Closed
Project Classification
Grow
Start Date
20-Apr-2017
Planning Date
01-Jun-2018
Delivery Date
28-Jun-2019
Close Date
26-Jul-2019
Overall Priority
Higher
Category
Compliance

Documentation