Report for November 2019
- Report Date
- November 2019
Summary
All UAT issues resolved apart new bug found in search.
Tayburn will also add the new Accessibility statement prepared for the project by Viki Galt.
Tayburn confirmed approach to deployment.
Achievements in Last Period
- UAT completion - not completed
- deployment - moved into December due to change freeze
Scope Changes
- n/a
Next Steps
- Sign off UAT
- Deploy December
- Close December
Future Milestones
Deliver | Work Package 1 | 29-Nov-2019 |
Deliver | Work Package 2 | 29-Nov-2019 |
Close | Closure | 15-Dec-2019 |
Sponsor Comment
no comment for this report
- Approved budget
- 0.0 days
- Activity this month
- 21.0 days
- Activity this year
- 7.0 days
- Activity to date
- 7.0 days
- Estimate to complete current year
- 4.0 days
- Estimate to complete future years
- 0.0 days