Report for June 2020

Report Date
June 2020

Project now Paused with no new Delivery Date provided to PM

Achievements in Last Period

  • Project Paused with no new Delivery Date
  • Magt changed dates to deliver now 31 Oct 20

Issues and Risks

Open issues currently impacting on the project timeline, budget or scope:

  • Project Delay - Due to Magt providing new Dates to conduct Implementation

Any current or imminent risks that need to be managed:

  • Project Delay - Due to Resource availability due to BAU and other Project work

  • Project Delay - Due to Magt providing new Dates to conduct Implementation

Next Steps

  • Revisit Mini-Cluster IS Alert

  • Revisit Go-CAB

  • Mini-Cluster Implementation

  • DF needs to confirm budget over spend has been sorted or provide direction

Future Milestones 

                         Milestone

 Date of Milestone

  9. Implement the recommended Samba Clustering (Date TBC by Magt)                                                                      

         Jun/Jul 19

         Jan 20

         27 Mar 20

         17 Apr 20

         01/10/20

  10. Transition Users to the new DataStore Infrastructure Configuration                                      

         Jun/Jul 19

          Jan 20

         27 Mar 20

         17 Apr 20

         01/10/20

  22. Delivery Complete

         28 Jun 19

         19 Jul 19  

       10 Feb 20

         27 Mar 20

         17 Apr 20

         01/10/20

  23. Acceptance

         26 Jul 19

        20 Feb 20

         03 Apr 20

         30 Apr 20

         30/10/20

  24. Closure  

         20 Jul 19

         26 Jul 19

         21 Feb 20

         03 Apr 20

         30 Apr 20

         30/10/20

  25. Closure Project

        28 Feb 20

        10 Apr 20

        30 Apr 20

        30/10/20

 

 

 

GUIDE TO RAG STATUS : project_planning_-_guide_to_rag_status.docx

Project Sponsor Commentary / Approval

- Approved

Project Status
RAG Status
Time
AMBER
Cost
GREEN
Scope
GREEN
Overall
GREEN
RAG Commentary
-Time is Amber due to Resource availability -Impact is no Infrastructure change -Return to Green will be when a new delivery date can be provided to the PM
Change Status
Time
No Change
Cost
No Change
Scope
No Change
Overall
No Change
Has formal escalation taken place?
Yes
Escalated to
Escalated to Project Sponsor and Programme Manager
Activity
Approved budget
178.0 days
Activity this month
0.4 days
Activity this year
27.3 days
Activity to date
69.1 days
Estimate to complete current year
108.9 days
Estimate to complete future years
0.0 days

Project Info

Project
Improving Access Interfaces for Compute and Data
Code
RSS051
Programme
ITI - Research Services (RSS)
Management Office
ISG PMO
Project Manager
Peter Sanderson
Project Sponsor
David Fergusson
Current Stage
Close
Status
Closed
Project Classification
Grow
Start Date
24-Sep-2018
Planning Date
30-Apr-2019
Delivery Date
14-Aug-2020
Close Date
28-Aug-2020
Programme Priority
3
Overall Priority
Normal
Category
Discretionary

Documentation