Report for August 2020

Report Date
August 2020

Project Closed - remaining activity to be completed as BAU

 

  • Revisit Mini-Cluster IS Alert

  • Revisit Go-CAB

  • Mini-Cluster Implementation

  • DF needs to confirm budget over spend has been sorted or provide direction

 

Project Status
RAG Status
Time
BLUE
Cost
BLUE
Scope
BLUE
Overall
BLUE
Change Status
Time
Within Tolerance
Cost
No Change
Scope
No Change
Overall
Within Tolerance
Has formal escalation taken place?
No
Activity
Approved budget
178.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
69.4 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Improving Access Interfaces for Compute and Data
Code
RSS051
Programme
ITI - Research Services (RSS)
Management Office
ISG PMO
Project Manager
Peter Sanderson
Project Sponsor
David Fergusson
Current Stage
Close
Status
Closed
Project Classification
Grow
Start Date
24-Sep-2018
Planning Date
30-Apr-2019
Delivery Date
14-Aug-2020
Close Date
28-Aug-2020
Programme Priority
3
Overall Priority
Normal
Category
Discretionary

Documentation