Report for June 2020
- Report Date
- June 2020
Achievements in Last Period
-
Management Changed the delivery date due to resource availability
-
Still limited work on Monitoring due to RSS Resources
-
Still no Prometheus meeting or Development
-
Still an issue with install-Escalated
-
UniDesk API chased; still in Test
Issues and Risks
Open issues currently impacting on the project timeline, budget or scope:
- Project Delay - Resource availability
Any current or imminent risks that need to be managed:
- Project Delivery - API’s Completion by APPS
-
Project Delay - Resource availability
-
Project Delivery - UniSight Issue
Next Steps
-
Resource API Resource
-
Implement IBM Monitoring Platform into RSS Platform
-
Solve Univa Issue
-
Complete rebuild and install of UniSight back end to connect to Prometheus
-
Prometheus Wksp, build VM's and complete connectivity
-
Transfer Univa Dash Boards to new User Platform
Future Milestones
Mile Stone |
Task Name |
% Complete |
Start |
Previous Dates |
Finish |
18 |
External Specific Accounting Configuration and Testing |
|
31/01/19 |
22/03/19 31/10/19 20/01/20 21/02/20 23/04/20 |
01/10/20 01/07/20 |
19 |
External Specific Accounting Configuration and Testing |
|
22/03/19 |
16/04/19 31/10/19 20/01/20 21/02/20 23/04/20 |
01/10/20 01/07/20
|
20 |
User Documentation and Testing |
|
16/04/19 |
21/05/19 20/01/20 21/02/20 23/04/20 |
01/10/20 01/07/20
|
21 |
Training for Customised Auditing and Monitoring Front End Service |
|
21/05/19 |
07/06/19 22/01/20 21/02/20 23/04/20 |
01/10/20 01/07/20
|
22 |
End of External Monitoring Service Configuration |
|
|
07/06/19 20/01/20 21/02/20 23/04/20 |
01/10/20 01/07/20
|
23 |
Release the New Monitoring Platforms |
|
18/03/19 |
30/05/19 22/01/20 23/04/20 |
01/10/20 01/07/20
|
11 |
RSS Training |
|
14/03/19 |
18/03/19 20/01/20 21/02/20 30/04/20 |
01/10/20 01/07/20
|
12 |
End of RSS Monitoring Service Platform Configuration |
|
|
18/03/19 20/02/20 28/02/20 30/04/20 |
18/10/20 09/07/20
|
24 |
Acceptance |
|
30/05/19 |
17/06/19 21/02/20 06/03/20 01/05/20 |
09/10/20 09/07/20
|
25 |
Closure Project |
|
17/06/19 |
24/06/19 28/02/20 13/03/20 08/05/20 |
30/10/20 31/07/20 |
GUIDE TO RAG STATUS : project_planning_-_guide_to_rag_status.docx
Project Sponsor Commentary / Approval
- Approved
- Approved budget
- 185.0 days
- Activity this month
- 0.6 days
- Activity this year
- 17.4 days
- Activity to date
- 96.7 days
- Estimate to complete current year
- 88.2 days
- Estimate to complete future years
- 0.0 days