Scheduler Upgrade

This project is to provide the implementation plan and process to bring the upgraded cluster batch scheduler which was identified and purchased in RSS033 into service with minimal disruption to users.

Current project status

Report Date RAG Budget Effort Completed Effort to complete
June 2020 BLUE 119.0 days 123.6 days 0.0

Project Info

Project
Scheduler Upgrade
Code
RSS055
Programme
ITI - Research Services (RSS)
Management Office
ISG PMO
Project Manager
Peter Sanderson
Project Sponsor
David Fergusson
Current Stage
Close
Status
Closed
Project Classification
Grow
Start Date
13-Aug-2018
Planning Date
28-Feb-2019
Delivery Date
08-May-2020
Close Date
12-Jun-2020
Overall Priority
Normal
Category
Discretionary

Documentation

Project Dashboard

Project journal

No entries found.

Change dashboard

Nothing to report.