Scheduler Upgrade - full project information

Current project status

Report Date RAG Budget Effort Completed Effort to complete
June 2020 BLUE 119.0 days 123.6 days 0.0
Content
Status
Closed
Current Stage
Close
Start Date
Monday, 13 August 2018
Planning Date
Thursday, 28 February 2019
Delivery Date
Friday, 8 May 2020
Close Date
Friday, 12 June 2020
Project information
Project Code
RSS055
Programme
ITI - Research Services (RSS)
Session
19/20
18/19
Organisational Unit
IS IT Infrastructure
Project Management Office (if relevant)
ISG PMO
Responsibility
IT Infrastructure
Project Category
Discretionary
Project Classification
Grow
Funding Source
DRS
Overall Priority
Normal
Student Impact
Project deliverables will have no impact on students