Report for May 2020

Report Date
May 2020

Achievements in Last Period

  • SVN Upgrade Implemented Successfully

  • Lessons Learnt held

Issues and Risks

Open issues currently impacting on the project timeline, budget or scope:

  • N/A

Any current or imminent risks that need to be managed:

  • N/A

Next Steps

  • Project Closure Report
  • Close the Project

Future Milestones

 

Mile

Stone

Task Name

% Complete

      Start

    Finish

16

  Vender Development on DEV

   100

  13/04/20

  17/04/20

17

  Vender Test Subversion DEV

   100

  20/04/20

  05/05/20

  24/04/20

18

  Subversion Upgrade on PROD and Test

   100

  28/04/20

   05/05/20

   30/04/20

19

  Delivery Complete   

   100

  28/04/20

  07/05/20

  30/04/20

20

  Acceptance

   100

  01/05/20

  08/05/20

21

  Closure Project

   0

  11/05/19

  29/05/19

  12/06/20

 

GUIDE TO RAG STATUS : project_planning_-_guide_to_rag_status.docx

Project Sponsor Commentary / Approval

- Approved

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Time
No Change
Cost
No Change
Scope
No Change
Overall
No Change
Has formal escalation taken place?
No
Activity
Approved budget
75.0 days
Activity this month
5.0 days
Activity this year
26.3 days
Activity to date
26.3 days
Estimate to complete current year
5.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Datasync Refresh
Code
RSS206
Programme
ITI - Research Services (RSS)
Management Office
ISG PMO
Project Manager
Peter Sanderson
Project Sponsor
David Fergusson
Current Stage
Close
Status
Closed
Project Classification
Run
Start Date
02-Sep-2019
Planning Date
04-Oct-2019
Delivery Date
30-Apr-2020
Close Date
12-Jun-2020
Programme Priority
1
Overall Priority
Highest
Category
Compliance