Completion Report
Project Summary
The scope of this project was to develop the new DRS Outreach Website http://www.digitalresearchservices.ed.ac.uk
- enhancements in response to feedback from the research community
- enhancements identified in the previous project RSS031 - work packages 1 - 7
- work package 1 and 2 implemented by RSS055
- accessibility compliance WP3
- further enhancements WP 4-7
Aiming to have an updated website by end of summer 2020.
The project identified seven work packages, which were estimated and costed by agency Tayburn.
Work Packages 3-7 were to be delivered by 2019-20 project RSS207 which is funded by 2020 DRS budget. WP7 was not initiated.
Work Packages 3-7 :
Updates to website to improve Accessibility Work Package 3 | Business lead Accessibility Officer | M | Objective 1 Deliverable 1.1 |
Updates to website to improve Navigation Work Package 4 | Business lead | S | Objective 1 Deliverable 1.2 |
Updates to website to improve Research In Action Work Package 5 | Business lead | S | Objective 1 Deliverable 1.3 |
Updates to website to improve Develop your Skills Work Package 6 | Business lead | S | Objective 1 Deliverable 1.4 |
Updates to website to improve Small items Work Package 7 | Business lead | S | Objective 1 Deliverable 1.5 |
Objectives and Deliverables and Success Criteria
Description of the Objective |
|||
Description of the Deliverables needed to achieve the objective | |||
Objective 1 |
Deliver Work Packages 3-7 by July 31st 2020 | Success Criteria | |
Deliverable D1.1 | Work Package 3 - Accessibility Enhancements | Approved by Accessibility Officer | Achieved |
Deliverable D1.2 |
Work Package 4 - Navigation | Approved by Business Lead | Achieved |
Deliverable D1.3 | Work Package 5 - Research in Action | Approved by Business Lead | Achieved |
Deliverable D1.4 | Work Package 6 - Develop your Skills | Approved by Business Lead | Achieved |
Deliverable D1.5 | Work Package 7 - Small items | Approved by Business Lead | Not Achieved |
Benefits
Benefits management and realisation will be available on the ITI Sharepoint space.
Analysis of Resource Usage:
Staff Usage Estimate: N/A
Explanation for variance:
Lessons Learned - Issues and Risks
No lessons learned to take forward other than agency had resource and comm issues during June-July.
Outstanding issues
None