Report for January 2020
- Report Date
- January 2020
Summary
Work Package 3 had been agreed and development scheduled for February.
Achievements in Last Period
- Initiate Project - Completed
- Project Brief - Completed
Issues and Risks
- no major issues or risks
Scope Changes
- none
Next Steps
- Development of Work Package 3 - Tayburn to confirm project timeline for development
Future Milestones
TBC
Sponsor Comment
no comment for this report
- Approved budget
- 100.0 days
- Activity this month
- 0.0 days
- Activity this year
- 0.0 days
- Activity to date
- 42.0 days
- Estimate to complete current year
- 32.0 days
- Estimate to complete future years
- 0.0 days