Report for February 2020

Report Date
February 2020

Summary

Work Package 3 had been agreed and development scheduled for March.

Achievements in Last Period 

  • Initiate Project - Completed
  • Project Brief - Completed

Issues and Risks

  • no major issues or risks

Scope Changes

  • a couple of minor enhancement added but no change in scope

Next Steps 

  • Development of Work Package 3 - Tayburn to confirm project timeline for development and UAT
  • Complete Development
  • Begin UAT

 

Future Milestones

 

WP3 - Accessibility - End of Planning 28-Feb-2020
WP3 - Accessibility - End of Build 20-Mar-2020
WP3 - Accessibility - End of UAT 26-Mar-2020
WP3 - Accessibility - Delivery 31-Mar-2020
Delivery of Last Work Package 03-Jul-2020
Closure 31-Jul-2020

 

 

 

Sponsor Comment

no comment for this report

 

 

 

 

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Time
Moderate
Cost
No Change
Scope
No Change
Overall
Moderate
Has formal escalation taken place?
No
Change Commentary
There has been a delay in purchasing additional servers for ECA and WGH - moving delivery back to June
Activity
Approved budget
30.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
4.0 days
Estimate to complete current year
26.0 days
Estimate to complete future years
0.0 days

Project Info

Project
DRS Outreach Website Development 19-20
Code
RSS207
Programme
ITI - Research Services (RSS)
Management Office
ISG PMO
Project Manager
Maurice Franceschi
Project Sponsor
David Fergusson
Current Stage
Close
Status
Closed
Project Classification
Grow
Start Date
13-Jan-2020
Planning Date
31-Jan-2020
Delivery Date
23-Jul-2020
Close Date
24-Jul-2020
Overall Priority
Highest
Category
Discretionary

Documentation