Report for February 2020
- Report Date
- February 2020
Summary
Work Package 3 had been agreed and development scheduled for March.
Achievements in Last Period
- Initiate Project - Completed
- Project Brief - Completed
Issues and Risks
- no major issues or risks
Scope Changes
- a couple of minor enhancement added but no change in scope
Next Steps
- Development of Work Package 3 - Tayburn to confirm project timeline for development and UAT
- Complete Development
- Begin UAT
Future Milestones
WP3 - Accessibility - End of Planning | 28-Feb-2020 |
WP3 - Accessibility - End of Build | 20-Mar-2020 |
WP3 - Accessibility - End of UAT | 26-Mar-2020 |
WP3 - Accessibility - Delivery | 31-Mar-2020 |
Delivery of Last Work Package | 03-Jul-2020 |
Closure | 31-Jul-2020 |
Sponsor Comment
no comment for this report
- Approved budget
- 30.0 days
- Activity this month
- 0.0 days
- Activity this year
- 0.0 days
- Activity to date
- 4.0 days
- Estimate to complete current year
- 26.0 days
- Estimate to complete future years
- 0.0 days