Report for March 2020

Report Date
March 2020

Summary

Work Package 3 had been agreed and development scheduled for March, with UAT starting 7th April.

Design mockups for WP4-5-6 to eb review w/c 6th April and this will help decide scope and design

Achievements in Last Period 

  • Development of Work Package 3 - On course for UAT by end of March - in progress
  • Decision to combine WP4/5/6 - taken
  • Outline project plan for WP4/5/6 agreed with Tayburn

Issues and Risks

  • no major issues or risks

Scope Changes

  • a couple of minor enhancement added but no change in scope

Next Steps 

  • WP3 UAT 
  • WP3 Deployment 
  • Design Approval for WP4/5/6

 

Future Milestones

 

WP3 - Accessibility - End of Build 06-Apr-2020
Work Packages 4-5-6 Design Review 17-Apr-2020
WP3 - Accessibility - End of UAT 17-Apr-2020
WP3 - Accessibility - Delivery 21-Apr-2020
WP4 - End of Design 04-May-2020
WP4 - End of Build 11-May-2020
WP4 - End of UAT 12-Jun-2020
WP4 - Delivery 15-Jun-2020
Closure 31-Jul-2020

 

 

 

 

Sponsor Comment

no comment for this report

 

 

 

 

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Time
No Change
Cost
No Change
Scope
No Change
Overall
No Change
Has formal escalation taken place?
No
Activity
Approved budget
30.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
4.0 days
Estimate to complete current year
26.0 days
Estimate to complete future years
0.0 days

Project Info

Project
DRS Outreach Website Development 19-20
Code
RSS207
Programme
ITI - Research Services (RSS)
Management Office
ISG PMO
Project Manager
Maurice Franceschi
Project Sponsor
David Fergusson
Current Stage
Close
Status
Closed
Project Classification
Grow
Start Date
13-Jan-2020
Planning Date
31-Jan-2020
Delivery Date
23-Jul-2020
Close Date
24-Jul-2020
Overall Priority
Highest
Category
Discretionary

Documentation