Report for May 2020
- Report Date
- May 2020
Summary
Work Package 4 had been agreed and development scheduled for May 2020
Temporary PM got up-to-speed with project
Achievements in Last Period
- Design mock ups for WP4 enhanced on test site
- UAT to commence once filters and agreed colours applied
Issues and Risks
- no major issues or risks
Scope Changes
- n/a
Next Steps
- WP34UAT
- WP4 Deployment
- Design Approval for WP 5/6
Future Milestones
WP4 - End of UAT | 12-Jun-2020 |
WP4 - Delivery | 15-Jun-2020 |
Closure | 31-Jul-2020 |
Sponsor Comment
no comment for this report
- Approved budget
- 30.0 days
- Activity this month
- 1.5 days
- Activity this year
- 1.5 days
- Activity to date
- 4.0 days
- Estimate to complete current year
- 26.0 days
- Estimate to complete future years
- 0.0 days