Report for June 2020

Report Date
June 2020

Summary

Work Package 4 in development 

Go Live date agreed and finalised

All stakeholders informed of Go live date

Supplier advised they unable to complete Go live date development 

Reassessed delivery timescale and await production of development work

Achievements in Last Period 

  • Some configuration changes and colours applied

Issues and Risks

  • Issue - Supplier did not meet delivery timescale

Scope Changes

  • n/a

Next Steps 

  • WP4 Deployment  including filters and agreed colours applied
  • WP4 testing
  • Confirmation of Go Live date to stakeholders
  • Design Approval for WP 5/6

 

Future Milestones

 

WP4 - End of UAT 12-Jun-2020
WP4 - Delivery 08-July-2020
Closure 31-Jul-2020

 

 

 

 

Sponsor Comment

no comment for this report

 

 

 

 

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Time
No Change
Cost
No Change
Scope
No Change
Overall
No Change
Has formal escalation taken place?
No
Activity
Approved budget
30.0 days
Activity this month
2.0 days
Activity this year
3.5 days
Activity to date
6.0 days
Estimate to complete current year
24.0 days
Estimate to complete future years
0.0 days

Project Info

Project
DRS Outreach Website Development 19-20
Code
RSS207
Programme
ITI - Research Services (RSS)
Management Office
ISG PMO
Project Manager
Maurice Franceschi
Project Sponsor
David Fergusson
Current Stage
Close
Status
Closed
Project Classification
Grow
Start Date
13-Jan-2020
Planning Date
31-Jan-2020
Delivery Date
23-Jul-2020
Close Date
24-Jul-2020
Overall Priority
Highest
Category
Discretionary