Report for June 2020
- Report Date
- June 2020
Summary
Work Package 4 in development
Go Live date agreed and finalised
All stakeholders informed of Go live date
Supplier advised they unable to complete Go live date development
Reassessed delivery timescale and await production of development work
Achievements in Last Period
- Some configuration changes and colours applied
Issues and Risks
- Issue - Supplier did not meet delivery timescale
Scope Changes
- n/a
Next Steps
- WP4 Deployment including filters and agreed colours applied
- WP4 testing
- Confirmation of Go Live date to stakeholders
- Design Approval for WP 5/6
Future Milestones
WP4 - End of UAT | 12-Jun-2020 |
WP4 - Delivery | 08-July-2020 |
Closure | 31-Jul-2020 |
Sponsor Comment
no comment for this report
- Approved budget
- 30.0 days
- Activity this month
- 2.0 days
- Activity this year
- 3.5 days
- Activity to date
- 6.0 days
- Estimate to complete current year
- 24.0 days
- Estimate to complete future years
- 0.0 days