Report for May 2020

Report Date
May 2020

Achievements in Last Period

  • Last Upgrade (to Train) Successfully Completed

Issues and Risks

Open issues currently impacting on the project timeline, budget or scope:

  • N/A

Any current or imminent risks that need to be managed:

  • N/A

Next Steps

  • Produce Project Closure Report
  • Close Project 

Future Milestones

Full Milestone Table as fist time reporting full plan

Mile

Stone

Task Name

 % Complete 

       Start

       Finish

16

  StackHPC Development on Eleanor DEV for 2nd Upgrade

          100

  11/05/20

  15/05/20

17

  StackHPC Test Eleanor DEV for 2nd Upgrade

          100

  18/05/20

  22/05/20

18

  Eleanor 2nd Upgrade on PROD and Test

          100

  25/05/20

  29/05/20

19

  Delivery Complete

          100

  29/05/20

  29/05/20

20

  Acceptance

          100

  01/06/20

  05/06/20

21

  Closure Project

            0

  08/06/20

  12/06/20

 

GUIDE TO RAG STATUS : project_planning_-_guide_to_rag_status.docx

Project Sponsor Commentary / Approval

- Approved

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Time
No Change
Cost
No Change
Scope
No Change
Overall
No Change
Has formal escalation taken place?
No
Activity
Approved budget
35.0 days
Activity this month
2.3 days
Activity this year
14.7 days
Activity to date
14.7 days
Estimate to complete current year
5.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Cloud Service
Code
RSS208
Programme
ITI - Research Services (RSS)
Management Office
ISG PMO
Project Manager
Peter Sanderson
Project Sponsor
David Fergusson
Current Stage
Close
Status
Closed
Project Classification
Transform
Start Date
02-Sep-2019
Planning Date
31-Oct-2019
Delivery Date
29-May-2020
Close Date
12-Jun-2020
Programme Priority
3
Overall Priority
Normal
Category
Discretionary