Report for June 2020

Report Date
June 2020

Achievements in Last Period

  • Project Closure Report Completed

  • Project Closed

Issues and Risks

Open issues currently impacting on the project timeline, budget or scope:

  • N/A

Any current or imminent risks that need to be managed:

  • N/A

Next Steps

  • N/A 

Future Milestones

Full Milestone Table as fist time reporting full plan

Mile

Stone

Task Name

 % Complete 

       Start

       Finish

21

  Closure Project

            100

  08/06/20

  12/06/20

 

GUIDE TO RAG STATUS : project_planning_-_guide_to_rag_status.docx

Project Sponsor Commentary / Approval

- Approved

Project Status
RAG Status
Time
BLUE
Cost
BLUE
Scope
BLUE
Overall
BLUE
Change Status
Time
No Change
Cost
No Change
Scope
No Change
Overall
No Change
Has formal escalation taken place?
No
Activity
Approved budget
35.0 days
Activity this month
4.5 days
Activity this year
19.2 days
Activity to date
19.2 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Cloud Service
Code
RSS208
Programme
ITI - Research Services (RSS)
Management Office
ISG PMO
Project Manager
Peter Sanderson
Project Sponsor
David Fergusson
Current Stage
Close
Status
Closed
Project Classification
Transform
Start Date
02-Sep-2019
Planning Date
31-Oct-2019
Delivery Date
29-May-2020
Close Date
12-Jun-2020
Programme Priority
3
Overall Priority
Normal
Category
Discretionary