Report for June 2021
- Report Date
- June 2021
Achievements in Last Period
-
Development sprints continue based on priorities set by User Team, Sponsor and Key Stakeholders.
-
Works completed seamlessly to DV Users against Oracle Gen1 to Gen2 Migration.
-
Works continuing against the following key tasks:
-
Business As Usual (BAU) / Bug fix tasks
-
Metadata / PURE Interface Works
-
-
Technical refactoring evaluation workshops were completed a draft options proposal is being finalised with the Technical Team.
-
The design document continues to be updated where required.
Risks/Issues
Issues:
Ref | Date Identified | Type | Title | Owner | Date of Last Review | |
---|---|---|---|---|---|---|
3 | 18-Mar-2020 | Issue | Project Related Disruption from Coronavirus | Kirsty Lingstadt | 30-Jun-2021 | |
Summary of current status of the issue:
Impact: Medium |
||||||
5 | 05-Oct-2020 | Issue | Storage Manager Certificate Issue | David Fergusson | 30-Jun-2021 | view |
Summary of current status of the issue: The issue is preventing a feature of the datavault service (adding public keys) from working. A workaround is temporarily in place with messaging. Jira - "RSS212-161 Analysis for options for adding key to Storage manager issue" - is being utilised to record findings against / look to resolve this issue.
Impact: Medium |
Risks:
None
Next Steps
-
Address any BAU priority bugs (if they arise).
-
Continue / complete development against the Metadata / PURE Interface works.
-
Complete an options paper / estimations for the refactoring DV IV code / infrastructure, following technical workshops.
-
Prepare for and conduct next Project Board, planned for 22-07-2021.
-
Closure of DV IV.
Milestones
Milestone | Due Date | Complete | |
---|---|---|---|
Requirements planning completed | 31-Jan-2020 | Yes | |
Project brief/planning completed | 14-Feb-2020 | Yes | |
Overall design work completed | 20-Mar-2020 | Yes | |
Performance improvements in operation | 28-Jul-2020 | Yes | |
Implement deposits from other file systems | 28-Jul-2020 | Yes | |
Further resilience & recovery in operation | 28-Jul-2020 | Yes | |
Retention date management released | 28-Jul-2020 | Yes | |
Migrate Oracle Cloud Platform from Gen 1 to Gen 2 | 23-Apr-2021 | Yes | view |
Evaluate encryption key management options | 11-Jun-2021 | No | view |
DV/Pure/UI improvements released | 26-Jul-2021 | No | view |
End of Agile Development / Deploy to Live Any Outstanding User Stories | 26-Jul-2021 | No | view |
Project closed | 28-Jul-2021 | No | view |
- Approved budget
- 318.0 days
- Activity this month
- 0.0 days
- Activity this year
- 0.0 days
- Activity to date
- 0.0 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 0.0 days