Report for April 2023
- Report Date
- April 2023
.Progress in Last Period
- Eddie GPU nodes (6) in operation, user testing completed, ready to bring into full service
- Further delays in bringing Eleanor GPU upgrades into service
- One Eleanor GPU hypervisor in operation, the second being configured
Risks/Issues
- RSS resource capacity is at risk as project (P2) will run in parallel with P1 projects (-)
- Further slippage encountered in Eleanor integration work (-)
- Planning of external supplier engagement is critical to progress (+)
- OCF will remove remaining legacy nodes when new nodes in service (+)
- Industrial action on future dates may impact resourcing and cause delays to progress (-)
- UCU marking boycott in progress; no impact at present (+)
Next Steps
- Bring Eddie GPU nodes (6) bring into service
- Complete configuration of 2nd Eleanor GPU hypervisor
- Geosciences and Physics will reuse legacy GPU cards if applicable
- Confirm date with OCF to uninstall legacy nodes
- Arrange for disposal of legacy GPU nodes
- Project closure in May
Milestones
Date | Milestone | Phase | Complete |
---|---|---|---|
05/05/2023 | Eddie GPU nodes brought into service | Deliver | No |
26/05/2023 | Eleanor GPU nodes brought into service | Deliver | No |
02/06/2022 | Project closed | Close | No |
- Approved budget
- 35.0 days
- Activity this month
- 1.5 days
- Activity this year
- 33.5 days
- Activity to date
- 70.5 days
- Estimate to complete current year
- 2.5 days
- Estimate to complete future years
- 0.0 days