Report for May 2023

Report Date
May 2023

.Progress in Last Period

  • Eddie GPU nodes (6) in operation
  • Eleanor GPU nodes (2) in operation
  • Project brief draft, reviewed, and approved

Risks/Issues

  • Not applicable

Next Steps

  • Decommission legacy GPU nodes (by OCF) (BAU)
  • Arrange for disposal of legacy GPU nodes (BAU)

Milestones

 

Date Milestone Phase Complete
05/05/2023 Eddie GPU nodes brought into service Deliver Yes
26/05/2023 Eleanor GPU nodes brought into service Deliver Yes
31/05/2022 Project closed Close Yes
Project Status
RAG Status
Time
BLUE
Cost
BLUE
Scope
BLUE
Overall
BLUE
Change Status
Time
No Change
Cost
No Change
Scope
No Change
Overall
No Change
Has formal escalation taken place?
No
Activity
Approved budget
35.0 days
Activity this month
2.5 days
Activity this year
36.0 days
Activity to date
73.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
GPU refresh
Code
RSS401
Programme
ITI - Research Services (RSS)
Management Office
ISG PMO
Project Manager
Lawrence Stevenson
Project Sponsor
David Fergusson
Current Stage
Close
Status
Closed
Project Classification
Run
Start Date
21-Oct-2021
Planning Date
03-Dec-2021
Delivery Date
26-May-2023
Close Date
31-May-2023
Programme Priority
2
Overall Priority
Higher
Category
Discretionary

Documentation