Infrastructure Refresh 21/22 - full project information

Current project status

Report Date RAG Budget Effort Completed Effort to complete
July 2022 GREEN 80.0 days 76.0 days 30.0
Content
Status
In Progress
Current Stage
Build
Start Date
Thursday, 21 October 2021
Planning Date
Friday, 10 December 2021
Delivery Date
Wednesday, 16 November 2022
Close Date
Wednesday, 14 December 2022
Project information
Project Code
RSS402
Programme
ITI - Research Services (RSS)
Session
22/23
21/22
Organisational Unit
IT Infrastructure
Project Management Office (if relevant)
ISG PMO
Responsibility
IT Infrastructure
Project Category
Discretionary
Project Classification
Run
Project Type
Infrastructure
Project Size
Large
Project Complexity
Standard
Alignment to Strategy 2030 and Adaptation & Renewal Team (ART)
Research
Funding Source
DRS
Programme Priority
1
Overall Priority
Highest
Student Impact
Project deliverables will be used by students