Project Status Reports

Title Report Date Time Cost Scope Overall Change
Report for July 2022 July 2022 GREEN GREEN GREEN GREEN Within Tolerance
Report for June 2022 June 2022 AMBER RED GREEN RED Significant
Report for May 2022 May 2022 AMBER AMBER GREEN GREEN Moderate
Report for April 2022 April 2022 GREEN GREEN GREEN GREEN Within Tolerance
Report for March 2022 March 2022 GREEN GREEN GREEN GREEN Moderate
Report for February 2022 February 2022 AMBER GREEN GREEN AMBER Within Tolerance
Report for January 2022 January 2022 GREEN GREEN GREEN GREEN Within Tolerance
Report for December 2021 December 2021 GREEN GREEN GREEN GREEN Within Tolerance
Report for November 2021 November 2021 GREEN GREEN GREEN GREEN Within Tolerance
Report for October 2021 October 2021 GREEN GREEN GREEN GREEN Within Tolerance

Project Info

Project
Infrastructure Refresh 21/22
Code
RSS402
Programme
ITI - Research Services (RSS)
Management Office
ISG PMO
Project Manager
Lawrence Stevenson
Project Sponsor
David Fergusson
Current Stage
Build
Status
In Progress
Project Classification
Run
Start Date
21-Oct-2021
Planning Date
10-Dec-2021
Delivery Date
16-Nov-2022
Close Date
14-Dec-2022
Programme Priority
1
Overall Priority
Highest
Category
Discretionary