Report for June 2022

Report Date
June 2022

 

Achievements in Last Period

  • Initiate - Project plan started
  • Received Proposal from Stack HPC
  • Received quote from Stack HPC
  • Scheduled start date

 

Issues and Risks

  • There is an emergent requirement to get Stack to translate from Ansible into Salt.
  • July budget cut off
  • STack HPC Technichal resource is not back from AL until 04/07/2021

Next Steps

  • Have requested that Stack HPC can assist in ansible translation and incorporate it into their current plan (at Cost to UoE)
  • Agree revised quote

Future Milestones

  • Receive revised quote
  • Receive revised proposal
  • Start

 

 

Project Sponsor Commentary / Approval

Project Status
RAG Status
Time
AMBER
Cost
AMBER
Scope
AMBER
Overall
AMBER
RAG Commentary
It is unlikely that CICD pipeline will be completed before the end of July as planned
Change Status
Time
Moderate
Cost
Moderate
Scope
Moderate
Overall
Moderate
Has formal escalation taken place?
Yes
Escalated to
David Fergusson
Change Commentary
Assumed 'Moderate' until actuals are received from the supplier Stack HPC.
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Interfaces to digital services
Code
RSS410
Programme
ITI - Research Services (RSS)
Management Office
ISG PMO
Project Manager
Morna Findlay
Project Sponsor
David Fergusson
Current Stage
Plan
Status
Suspended
Project Classification
Run
Start Date
12-May-2025
Planning Date
02-Jun-2025
Delivery Date
21-Jul-2025
Close Date
25-Aug-2025
Overall Priority
Normal
Category
Discretionary