Report for June 2024
- Report Date
- June 2024
Programme Owner confirms that project is to not to restart from suspension until the resource situation improves – staff currently assigned to higher priority work/projects.
Scheduled Q4 2024
Achievements in Last Period
- Resource constrained, unable to move forward at this time.
- Chased department leads for future availability, request is being considered
- Will revisit resourcing monthly
Issues and Risks
- Due to resource constraints we are unable to consider the Ansible/SALT translation
Next Steps
- Await resource availability
Future Milestones
- Begin translation analysis
- Start
Project Sponsor Commentary / Approval
- Approved budget
- 0.0 days
- Activity this month
- 0.0 days
- Activity this year
- 0.0 days
- Activity to date
- 0.0 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 0.0 days