This project will deliver the replacement of the fibre channel (FC) infrastructure supporting the DataStore service at the Mary Somerville (formerly JCMB) Data Centre. The scope covers installation, testing and replacement of fibre channel cabling, trunking, switches, and other components in the network. In addition, the scope includes the removal and disposal of legacy fibre channel equipment once the new infrastructure is in operation.

The main goals of the work are to replace end-of-life (EOL) equipment, add to the available fibre channel capacity, and improve the performance of the network. A key objective is to replace the fibre channel network whilst minimising the reduction in availability and performance of DataStore services. This work has been identified as a Priority 1 project ensuring compliance, additional capacity, and improved performance across the DataStore fibre channel network at the Mary Somerville Data Centre (MSDC).

It is estimated that the project will run from August to October 2022 and will require significant Research Services (RSS) staff involvement for specification of requirements, procurement and supplier management, installation planning and delivery, installation and configuration, testing, commissioning, and disposal of EOL equipment. In addition, support will be required for data centre planning and installation in collaboration with the MSDC manager.

It should be noted that the completion of this project is a prerequisite for the continuation of other planned DataStore work e.g. the DataStore server and storage upgrade streams in RSS402 Infrastructure Refresh 2021/22.

Monthly reports, milestones, risks and issues, etc. will be available on this website. Additional documentation will be stored at the project SharePoint site. Project tasks will be managed and tracked on a Jira Scrum dashboard and backlog.

Current project status

Report Date RAG Budget Effort Completed Effort to complete
February 2023 BLUE 48.0 days 50.0 days 0.0

Project Info

Project
DataStore Fibre Channel Replacement
Code
RSS501
Programme
ITI - Research Services (RSS)
Management Office
ISG PMO
Project Manager
Lawrence Stevenson
Project Sponsor
David Fergusson
Current Stage
Close
Status
Closed
Project Classification
Run
Start Date
09-Aug-2022
Planning Date
31-Aug-2022
Delivery Date
17-Feb-2023
Close Date
24-Feb-2023
Overall Priority
Higher
Category
Compliance

Documentation

Project Dashboard

Project journal

No entries found.

Change dashboard

Nothing to report.