Report for June 2013
- Report Date
- June 2013
Achievements in Last Period
- SDS completed and signed off
- Development and testing resource allocated
- SDS completed and signed off
- Milestone set for Delivery mid-July 2013
- SITS config changes, SQL scripts and BOXI changes completed in Dev
- SITS config changes Deployed to test
Issues
- BOXI/SQL Config changes deployment to test is dependant on other project priorities and thus disenganged from the SITS config changes. All changes need to go into Live at the same time in order for this change to work.
Next Steps
- Deploy to Test SQL/Boxi changes
- Complete all testing and sign-off
- Conduct Implementation meetings and sign-off by DevTech and AppsMgt
- Deliver to Live
- Wrap up project
Milestones
01-Jul-2013 | Phase 3 - Deploy to Test SITS Config | Integrate | Yes | edit | view |
01-Jul-2013 | Phase 3- Build Sign-off SITS config Changes | Build | Yes | edit | view |
10-Jul-2013 | Phase 3 Build Sign-off - Boxi/Scripts | Build | No | edit | view |
11-Jul-2013 | Phase 3 Deploy to test - Boxi/Scripts | Integrate | No | edit | view |
15-Jul-2013 | Phase 3- Acceptance Sign-off | Accept | No | edit | view |
18-Jul-2013 | Phase 3 - Deliver to Live | Deliver | No | edit | view |
- Approved budget
- 83.0 days
- Activity this month
- 6.0 days
- Activity this year
- 64.0 days
- Activity to date
- 69.0 days
- Estimate to complete current year
- 15.0 days
- Estimate to complete future years
- 0.0 days