Report for July 2013
- Report Date
- July 2013
Achievements in Last Period
- SITS BOXI/SQL changes for final Phase 3 (Tribal Fields upgrade) delivered into Live mid July
Issues
None
Next Steps
- SAC002 Closure Report need to be completed.
- Communicate to relevant Stakeholders how outstanding items not delivered in SAC002 have been integrated into SAC020
- Offically mark project as Closed Early August
- Approved budget
- 83.0 days
- Activity this month
- 3.0 days
- Activity this year
- 68.0 days
- Activity to date
- 73.0 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 0.0 days