Report for May 2013
- Report Date
- May 2013
Achievements in Last Period
- All outstanding KIS issues not to be completed in SAC002 transferred to SAC020 as user stories
- Milestones set for August Delivery of SAc002 Phase 3
Issues
- Potential lack of resource of SSP to complete SDS in June
Next Steps
- Complete SDS and commence build of Phase 3
Milestones
17-Jun-2013 | Phase 3 SDS complete | Design | |||
15-Jul-2013 | Phase 3- Build Sign-off | Build | |||
22-Jul-2013 | Phase 3 - Deploy to Test | Integrate | |||
05-Aug-2013 | Phase 3- Acceptance Sign-off | Accept | |||
12-Aug-2013 | Phase 3 - Deliver to Live | Deliver |
- Approved budget
- 114.0 days
- Activity this month
- 0.3 days
- Activity this year
- 58.5 days
- Activity to date
- 63.5 days
- Estimate to complete current year
- 18.7 days
- Estimate to complete future years
- 0.0 days