Report for May 2013

Report Date
May 2013

Achievements in Last Period

  • All outstanding KIS issues not to be completed in SAC002 transferred to SAC020 as user stories
  • Milestones set for August Delivery of SAc002 Phase 3

Issues

  • Potential lack of resource of SSP to complete SDS in June  

Next Steps

  • Complete SDS and commence build of Phase 3  

Milestones

 

17-Jun-2013Phase 3 SDS completeDesign   
15-Jul-2013Phase 3- Build Sign-offBuild   
22-Jul-2013Phase 3 - Deploy to TestIntegrate   
05-Aug-2013Phase 3- Acceptance Sign-offAccept   
12-Aug-2013Phase 3 - Deliver to LiveDeliver   

 

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
114.0 days
Activity this month
0.3 days
Activity this year
58.5 days
Activity to date
63.5 days
Estimate to complete current year
18.7 days
Estimate to complete future years
0.0 days

Project Info

Project
Key Information Sets
Code
SAC002
Programme
Student Systems Partnership SSP
Project Manager
Duncan Scott
Project Sponsor
Susan Rigby
Current Stage
Close
Status
Closed
Start Date
12-Mar-2012
Planning Date
n/a
Delivery Date
n/a
Close Date
12-Aug-2013
Overall Priority
Normal
Category
Discretionary

Documentation